When a plumbing repair changes, describe the extra work, revised contract price and schedule impact in a written change order. Get approval from the person authorised to change the agreement before completing the new scope.

Pause at the first change in scope

Record the unexpected condition while it is visible. Describe the options in plain language and give the difference in cost and timing for each. Confirm who has authority to approve the extra work. Keep that reply with the original estimate so the office can explain the invoice later.

In practice

The shut-off also leaks. Photograph its condition and provide a separate line for replacing and testing it.

What if the owner cannot be reached?

Use the contact and spending authority agreed before the job. Document the discovery and the state in which work paused. Avoid treating silence as approval for a wider scope, even when the additional work seems obvious.

Separate newly discovered work from the original quote

Identify the original scope item, the site condition that changed it and the point where work stopped. Show added and omitted work separately, with the net cost and timing impact. If there are two reasonable options, explain what each delivers. Obtain a dated approval from the authorised contact and keep the photo or inspection note that prompted the change. At closeout, reference the change number on the invoice so the customer can follow the calculation.

Record what changed on the renovation project

Open the original written contract or estimate and identify the precise item that no longer applies. Suppose the contract covers replacing a tap. Once the existing fixture is removed, the technician finds an inaccessible or damaged shutoff that needs separate work. Record what was visible before work began, what you found and where the job paused. A photo can support the description, but the homeowner should understand the condition without interpreting a picture of a pipe.

Identify the change in work, price and materials

Use a reference that ties the change order to the original project. Describe the original work, the added work and any labour or materials removed from the scope. Give the amount added or credited, applicable tax and the revised contract price. If the new work requires a different part or permit, state who checks the requirements and how that affects the renovation schedule. Identify the tasks an owner or another contractor must finish before your technician can resume.

Offer a decision the homeowner can make

Explain what each option delivers. For example, an owner might approve replacement of the affected fitting and a return visit after the correct part arrives. Or the customer may approve a diagnostic visit and request a price for repair once the conditions are known. Describe anything the extra work will not correct. If the homeowner pauses the project, agree what happens to the work already completed and when you will discuss the next step.

Use written approval you can find at invoicing

Include the address, customer, contractor, date, original quote number and change order number. Identify the person with permission to approve changes. In an occupied rental or condo, the person present may be able to grant access without authorising a price change. Send the written proposal to the correct contact and keep their approval with the project record. When billing, show the extra line with the change order reference, approved amount and any credits.

A short example for a residential plumbing repair

“Change 02 to estimate 104. Wall connection found damaged when removing the old trap. Add replacement connection and leak test. Cabinet restoration stays outside this scope. Example price is CAD 140 before applicable tax. The planned visit requires another 45 minutes if the owner approves and access remains available.” Use figures agreed for the actual job and include the revised total so the customer can see the full price.

Plumbing change order form: what to fill in

Use one numbered change order form for each decision. Show the original job number, request date, proposed start date, new scope, schedule impact and change in total. On a second line show the updated contract total. Add a place for the contractor and customer to sign and date the change order. If the request arrives by text, move the details into the written change order so the signed approval identifies the same scope, price and schedule.

From signed change order to invoice

After the change order is signed, update the job schedule and send the technician the new instructions. Keep the change order in the job file and put its number beside the related line on the invoice. If the job requires progress payments, show which invoice includes the change and how it affects the remaining total. Date any update and let the customer see how the schedule moves before assigning a new start date.

When do you need one change order per job?

Use one change order for each decision that changes the contract total or moves the schedule. Before extra work starts, state whether the cost is billed separately or included in the next progress invoice. On the form, show the cost of removed work and add the new work. The change order total is the difference. Put the new contract total below it so the customer and contractor can check both numbers.

What if the customer approves by text?

If the contract permits text approval, keep the message beside the change order with the same price and scope. If a signature is required, get the signature before additional work starts. Set the status to approved, update the schedule and let the contractor see which change order may now be billed.

What to check next

Attach the approval to the original quote. When billing, use the same description so the customer can match the extra work to the decision.